Extra material: Maintenance planning

Problem statement

A process unit is operating over a maintenance planning horizon from 11 to TT days. On day tt the unit makes a profit ctc_t which is known in advance. The unit needs to shut down for PP maintenance periods during the planning period. Once started, a maintenance period takes MM days to finish.

Find a maintenance schedule that allows the maximum profit to be produced.

Preamble: Install Pyomo and a solver

The following cell sets and verifies a global SOLVER for the notebook. If run on Google Colab, the cell installs Pyomo and the HiGHS solver, while, if run elsewhere, it assumes Pyomo and HiGHS have been previously installed. It then sets to use HiGHS as solver via the appsi module and a test is performed to verify that it is available. The solver interface is stored in a global object SOLVER for later use.

import sys if 'google.colab' in sys.modules: %pip install pyomo >/dev/null 2>/dev/null %pip install highspy >/dev/null 2>/dev/null solver = 'appsi_highs' import pyomo.environ as pyo SOLVER = pyo.SolverFactory(solver) assert SOLVER.available(), f"Solver {solver} is not available."
import matplotlib.pyplot as plt import numpy as np import pandas as pd import pyomo.gdp as gdp

Modeling with disjunctive constraints

The model comprises two sets of the binary variables indexed by the day tt, with t=1,,Tt=1,\dots,T. Binary variables xtx_t correspond to the operating mode of the process unit, with xt=1x_t=1 indicating the unit is operating on day tt and able to earn a profit ctc_t. Binary variable yt=1y_t=1 indicates the first day of a maintenance period during which the unit is not operating and earning 00 profit.

Objective

The planning objective is to maximize profit realized during the TT days the plant is operational. This is achieved by maximizing the sum of the products of the profit per day ctc_t and the binary variable xtx_t indicating the unit is operating on that day.

Profit=t=1Tctxt\begin{align*} \text{Profit} & = \sum_{t=1}^T c_t x_t \end{align*}

Constraints

Number of maintenance periods is equal to P.

Completing PP maintenance periods requires a total of PP starts.

t=1Tyt=P\begin{align*} \sum_{t=1}^T y_t & = P \\ \end{align*}

Maintenance periods do not overlap.

No more than one maintenance period can start in any consecutive set of MM days.

s=0M1yt+s1t=1,2,,TM+1\begin{align*} \sum_{s=0}^{M-1}y_{t+s} & \leq 1 \qquad \forall \, t = 1, 2, \ldots, T-M+1 \end{align*}

This last requirement could be modified if some period of time should occur between maintenance periods.

The unit must shut down for M days following a maintenance start.

The final requirement is a disjunctive constraint that says either yt=0y_t = 0 or the sum s=0M1xt+s=0\sum_{s=0}^{M-1}x_{t+s} = 0, but not both. Mathematically, this forms a set of constraints reading

(yt=0)(s=0M1xt+s=0)t=1,2,,TM+1\begin{align*} \left(y_t = 0\right) \veebar \left(\sum_{s=0}^{M-1}x_{t+s} = 0\right)\qquad \forall \, t = 1, 2, \ldots, T-M+1 \end{align*}

where \veebar denotes an exclusive OR condition.

Pyomo implementation

Pyomo model

The disjunctive constraints can be represented directly in Pyomo using the Generalized Disjunctive Programming extension. The GDP extension transforms the disjunctive constraints to a mixed integer linear optimization (MILO) problem using convex hull and cutting plane methods.

def maintenance_planning(c, M, P): m = pyo.ConcreteModel("Maintenance planning") T = len(c) m.T = pyo.RangeSet(1, T) m.Y = pyo.RangeSet(1, T - M + 1) m.S = pyo.RangeSet(0, M - 1) m.c = pyo.Param(m.T, initialize=c) m.x = pyo.Var(m.T, domain=pyo.Binary) m.y = pyo.Var(m.T, domain=pyo.Binary) @m.Objective(sense=pyo.maximize) def profit(m): return sum(m.c[t] * m.x[t] for t in m.T) @m.Constraint() def required_maintenance(m): return P == sum(m.y[t] for t in m.Y) @m.Constraint(m.Y) def no_overlap(m, t): return sum(m.y[t + s] for s in m.S) <= 1 @m.Disjunction(m.Y, xor=True) def required_shutdown(m, t): return [[m.y[t] == 0], [sum(m.x[t + s] for s in m.S) == 0]] pyo.TransformationFactory("gdp.hull").apply_to(m) SOLVER.solve(m) return m def plot_schedule(m): tab20 = plt.get_cmap("tab20", 20) colors = [tab20(i) for i in [0, 2, 4, 6]] fig, ax = plt.subplots(3, 1, figsize=(12, 6)) ax[0].bar(m.T, [m.c[t] for t in m.T], color=colors[0]) ax[0].set_title("Daily profit $c_t$") ax[1].bar(m.T, [m.x[t]() for t in m.T], color=colors[2]) ax[1].set_title("Optimal operating schedule $x_t$") ax[1].set_ylabel("Capacity used") ax[2].bar(m.Y, [m.y[t]() for t in m.Y], color=colors[3]) ax[2].set_title("Optimal maintenance starting moments $y_t$") ax[2].yaxis.set_ticks([]) ax[2].yaxis.set_ticklabels([]) for a in ax: a.set_xlim(0.1, len(m.T) + 0.9) a.set_xlabel("Days") plt.tight_layout() # setting problem parameters T = 90 # planning horizon M = 3 # length of maintenance period P = 4 # number of maintenance periods # create a random number generator rng = np.random.default_rng(2023) # use the random number generator to generate random daily profits c = {k: rng.uniform() for k in range(1, T + 1)} model = maintenance_planning(c, M, P) plot_schedule(model)
Image in a Jupyter notebook

Ramping constraints

Prior to maintenance shutdown, a large processing unit may take some time to safely ramp down from full production. Furthermore, it also requires more time to safely ramp back up to full production after maintenance. To account for ramp-down and ramp-up periods, we modify the problem formation in the following ways.

  • The variable denoting unit operation, xtx_t is changed from a binary variable to a continuous variable 0xt10 \leq x_t \leq 1 denoting the fraction of total capacity at which the unit is operating on day tt.

  • Two new variable sequences, 0ut+ut+,max0 \leq u_t^+ \leq u_t^{+,\max} and 0utut,max0\leq u_t^- \leq u_t^{-,\max}, are introduced which denote the fraction increase or decrease in unit capacity to completed on day tt.

  • An additional sequence of equality constraints is introduced relating xtx_t to ut+u_t^+ and utu_t^-:

xt=xt1+ut+utt=1,2,,T1.\begin{align*} x_{t} & = x_{t-1} + u^+_t - u^-_t \quad \forall \, t = 1, 2, \ldots, T-1. \end{align*}

We begin the Pyomo model by specifying the constraints, then modifying the Big-M formulation to add the features described above.

# Parameters for ramping constraints upos_max = 0.3334 uneg_max = 0.5000 def maintenance_planning_ramp(c, M, P): m = pyo.ConcreteModel("Maintenance planning with ramping constraints") T = len(c) m.T = pyo.RangeSet(1, T) m.Y = pyo.RangeSet(1, T - M + 1) m.S = pyo.RangeSet(0, M - 1) m.c = pyo.Param(m.T, initialize=c) m.x = pyo.Var(m.T, bounds=(0, 1)) m.y = pyo.Var(m.T, domain=pyo.Binary) m.upos = pyo.Var(m.T, bounds=(0, upos_max)) m.uneg = pyo.Var(m.T, bounds=(0, uneg_max)) @m.Objective(sense=pyo.maximize) def profit(m): return sum(m.c[t] * m.x[t] for t in m.T) @m.Constraint() def required_maintenance(m): return P == sum(m.y[t] for t in m.Y) @m.Constraint(m.Y) def no_overlap(m, t): return sum(m.y[t + s] for s in m.S) <= 1 @m.Disjunction(m.Y, xor=True) def required_shutdown(m, t): return [[m.y[t] == 0], [sum(m.x[t + s] for s in m.S) == 0]] @m.Constraint(m.T) def ramp(m, t): if t == 1: return pyo.Constraint.Skip else: return m.x[t] == m.x[t - 1] + m.upos[t] - m.uneg[t] pyo.TransformationFactory("gdp.hull").apply_to(m) SOLVER.solve(m) return m m = maintenance_planning_ramp(c, M, P) plot_schedule(m)
Image in a Jupyter notebook

Specifying the minimum number of operational days between maintenance periods

Up to this point we have imposed no constraints on the frequency of maintenance periods. Without such constraints, particularly when ramping constraints are imposed, is that maintenance periods will be scheduled back-to-back, which is clearly not a useful result for most situations.

The next revision of the model is to incorporate a requirement that NN operational days be scheduled between any maintenance periods. This does allow for maintenance to be postponed until the very end of the planning period. The disjunctive constraints read

(yt=0)(s=0(M+N1)(t+sT)xt+s=0)t=1,2,,TM+1\begin{align*} \left(y_t = 0\right) \veebar \left(\sum_{s=0}^{(M + N -1) \wedge (t + s \leq T)}x_{t+s} = 0\right)\qquad \forall t = 1, 2, \ldots, T-M+1 \end{align*}

where the upper bound on the summation is needed to handle the terminal condition.

Paradoxically, this is an example where the Big-M method provides a much faster solution.

s=0(M+N1)(t+sT)xt+s(M+N)(1yt)t=1,2,,TM+1\begin{align*} \sum_{s=0}^{(M + N -1) \wedge (t + s \leq T)}x_{t+s} \leq (M+N)(1-y_t) \qquad \forall t = 1, 2, \ldots, T-M+1 \end{align*}

The following cell implements both sets of constraints.

# Set the minimum number of operational days between maintenance periods N = 10 def maintenance_planning_ramp_operational(c, T, M, P, N): m = pyo.ConcreteModel( "Maintenance planning with ramping constraints and minimum operational days" ) m.T = pyo.RangeSet(1, T) m.Y = pyo.RangeSet(1, T - M + 1) m.S = pyo.RangeSet(0, M - 1) m.W = pyo.RangeSet(0, M + N - 1) m.c = pyo.Param(m.T, initialize=c) m.x = pyo.Var(m.T, bounds=(0, 1)) m.y = pyo.Var(m.T, domain=pyo.Binary) m.upos = pyo.Var(m.T, bounds=(0, upos_max)) m.uneg = pyo.Var(m.T, bounds=(0, uneg_max)) @m.Objective(sense=pyo.maximize) def profit(m): return sum(m.c[t] * m.x[t] for t in m.T) # ramp constraint @m.Constraint(m.T) def ramp(m, t): if t > 1: return m.x[t] == m.x[t - 1] + m.upos[t] - m.uneg[t] return pyo.Constraint.Skip # required number P of maintenance starts @m.Constraint() def sumy(m): return sum(m.y[t] for t in m.Y) == P # no more than one maintenance start in the period of length M @m.Constraint(m.Y) def sprd(m, t): return sum(m.y[t + s] for s in m.W if t + s <= T) <= 1 # Choose one or the other the following methods. Comment out the method not used. # Disjunctive constraint # @m.Disjunction(m.Y) # def disj(m, t): # return [m.y[t] == 0, # sum(m.x[t+s] for s in m.W if t + s <= T) == 0] # pyo.TransformationFactory('gdp.bigm').apply_to(m) # big-M method @m.Constraint(m.Y) def bigm(m, t): return sum(m.x[t + s] for s in m.S) <= (M + N) * (1 - m.y[t]) SOLVER.solve(m) return m m = maintenance_planning_ramp_operational(c, T, M, P, N) plot_schedule(m)
Image in a Jupyter notebook

Exercises

  1. Rather than specify how many maintenance periods must be accommodated, modify the model so that the process unit can operate no more than NN days without a maintenance shutdown. (Hint. You may to introduce an additional set of binary variables, ztz_t to denote the start of an operational period.)

  2. Do a systematic comparison of the Big-M, Convex Hull, and Cutting Plane techniques for implementing the disjunctive constraints. Your comparison should include a measure of complexity (such as the number of decision variables and constraints in the resulting transformed problems), computational effort, and the effect of solver (such as HiGHS vs cbc).